Woodland West Library Remodel – $395,000

This funding would allow for remodeling of the entryway and addition of approximately 600 square feet to the Woodland West Library. Current spending schedule:

Design
2017: $45,000

Construction
2018: $350,000

Elements of Architecture is the firm selected to do the design work. Design work is in progress and will be complete this fiscal year. Construction is slated for 2018.

Library Portion of the Hugh Smith Recreation Center/East Library Project – $5,695,000

This funding would allow for design and construction of a new East Arlington Branch Library, which will be co-located with a reconstructed Hugh Smith Recreation Center. Current spending schedule:

Construction
2017: $5,695,000