Arlington voters approved a five-year, $236 million bond package that focuses on streets, parks, fire facilities and libraries. Check here to track each project’s budget and construction timelines.

Libraries

Bond-Libraries

Woodland West Library Remodel – $395,000

This funding would allow for remodeling of the entryway and addition of approximately 600 square feet to the Woodland West Library. Current spending schedule:

Design
2016: $45,000

Construction
2018: $350,000

Library Portion of the Hugh Smith Recreation Center/East Library Project – $5,695,000

This funding would allow for design and construction of a new East Arlington Branch Library, which will be co-located with a reconstructed Hugh Smith Recreation Center. Current spending schedule:

Construction
2017: $5,695,000