UP Rail Crossing Closures January 16-24, 2015

2015 UPRR Flyer

Click here to view flyer

Drivers should expect minor detours and railroad crossing closures when the next phase of the Union Pacific track renewal project returns to Arlington.

Project Dates

Here is the most recent rail crossing closure schedule provided by Union Pacific:

Center & Mesquite
Closure 1/16 at 6 p.m. – Opening 1/18 at 7 a.m.
Detours: Collins, Cooper
View Phase 1 Map

Cooper & Davis
Closure 1/18 at 6 p.m. – Opening 1/20 at 7 a.m.
Detours: Center, Bowen
View Phase 2 Map

Great Southwest & Bowen
Closure 1/20 at 6 p.m. – Opening 1/22 at 7 a.m.
Detours: SH360, Davis
View Phase 3 Map

Collins
Closure 1/22 at 6 p.m. – Opening 1/24 at 7 a.m.
Detours: Center, Mesquite, Stadium
View Phase 4 Map

– Dates are subject to change

Project Facts

During this phase of the project, crews will replace the south mainline rail, crossties and ballast on the 13-mile stretch of rail which runs parallel to Division Street. Concrete panels at each railroad crossing will be renewed as well.

    • Crews are expected to work from 7:00 p.m. to 4 a.m. each day.
    • Trains passing by work crews will blow their horns for safety reasons, even in the quiet zones.
    • Only two railroad crossings will be closed at a time. This will help minimize the impact on northbound and southbound traffic.

Project Maps

The following crossings will remain OPEN during the extent of the project:

UPRR Open Crossings Map

Explore our Arlington Webcam Map Tour, list of webcams or news archive to help you plan your daily commute.

Questions?

FAQLatest News | Arlington Action Center 817-459-6777

For the latest information on the UP track renewal project and updated maps of the roadways as they are closed, follow us on Twitter @CityOfArlington #TrackRenewal, sign up for email “Daily Updates” at MyArlingtonTx.com.