Planned and emergency projects to keep Arlington’s water and sewer infrastructure strong.

2017 Water Main Renewals

Click on map to enlarge.

This project includes the replacement of approximately 21,000 feet of 6-inch and 8-inch water mains in various Arlington locations by the pipe bursting method. The construction method involves pipe bursting the existing 6-inch or 8-inch water main while pulling a new 8-inch main through the existing pipe. The process is trenchless and requires limited excavation which minimizes construction time and disruption to customers. These improvements will replace aging infrastructure with a history of water main breaks which will reduce maintenance costs and improve service to this area. For more details about the pipe bursting process, click here.

The areas included in the project are below. The projects in bold were complete or near completion by May 2018.

  • High Point Road (Arbrook Blvd. to S. Cooper St.) – Construction begins Nov. 6, 2017 and is expected to continue through January 2018. (Neighborhood map) (Information on sanitary sewer replacements)
  • New Haven St. (Skyline Dr. to Road to Six Flags St.)
  • Altman Drive (Center St. to end of Altman)
  • Timberlake Drive (Pioneer Parkway to Grand Prairie City Limit)
  • 113th St. (Ave E East to end of street)
  • Mitchell St. (Sunnyvale Drive to New York Drive)
  • Skylark Drive (Mitchell Street to Browning Drive)
  • Thannisch Drive (Center St. to Randol Mill Road)

Click here to learn more about previous pipe bursting projects in Arlington.

Project status: The Arlington City Council approved a construction contract not to exceed $2,556,340 with Murphy Pipeline Contractors, Inc., of Jacksonville, Florida in early October. Construction begins on High Point Drive on Nov. 6, 2017. The street locations above are listed in the order in which construction is set to progress.

Related closures and outages: Some short-term water outages and lane closures are expected during the project. Affected residents will be notified through face-to-face interactions, social media, and email communication.

Timeline: The construction contract time is 275 days. However, each location has an individual timeline.